Item Coversheet
CITY OF WATERLOO

Council Communication

Motion approving Change Order No. 3 for a net decrease of $111,705.70 for Rehabilitation of Taxiway E for the Waterloo Regional Airport; and authorize the Mayor to execute said document.

City Council Meeting: 12/15/2014
Prepared: 12/8/2014
ATTACHMENTS:
DescriptionType
Change OrderBackup Material
Submitted by:
Submitted By: Keith Kaspari, Direction of Aviation
Recommended Action:

Approval of change order.

Background Information:

The final change order decreases the contract with Aspro, Inc. and adjusts all contract quantities to match field measurements for quantities installed.  It also adjusts payment percentage on Bituminous Leveling Course Lot #1, which did not meet requirements.  Contractor chose to leave bituminous payment in place and take a 50 percent reduction in payment.  It was reviewed and approved by FAA.