CITY OF WATERLOO

Council Communication

Resolution approving Completion of Project, Recommendation of Acceptance of Work and release of retainage in the amount of $5,759.10 for work performed by Vieth Construction Corporation of Cedar Falls, Iowa, at a total cost of $115,181.98, for the South Hills Drainage Improvements.

City Council Meeting: 12/22/2014
Prepared: 12/16/2014
ATTACHMENTS:
DescriptionType
South Hills Drainage ImprovementsCover Memo
SUBJECT:

Resolution approving Completion of Project, Recommendation of Acceptance of Work and release of retainage in the amount of $5,759.10 for work performed by Vieth Construction Corporation of Cedar Falls, Iowa, at a total cost of $115,181.98, for the South Hills Drainage Improvements.

Submitted by:
Submitted By: JB Bolger, Golf & Downtown Area Maintenance Manager
Summary Statement:

Final payment reflects a net decrease of $3,818.02.

Expenditure Required:

$115,181.98

Source of Funds:

Capital Improvement Golf Course Improvement Bond Funds

Background Information:

This project addresses storm water runoff from the Sweetwater Circle/South Fork Lane neighborhood by installing 36" concrete storm sewer pipe under holes 14 and 15.