Resolution approving Completion of Project, Recommendation of Acceptance of Work and release of retainage in the amount of $5,759.10 for work performed by Vieth Construction Corporation of Cedar Falls, Iowa, at a total cost of $115,181.98, for the South Hills Drainage Improvements.
City Council Meeting: 12/22/2014 Prepared: 12/16/2014 |
| | | | | | | | SUBJECT:
| Resolution approving Completion of Project, Recommendation of Acceptance of Work and release of retainage in the amount of $5,759.10 for work performed by Vieth Construction Corporation of Cedar Falls, Iowa, at a total cost of $115,181.98, for the South Hills Drainage Improvements. |
|
| | | | | | | | Submitted by:
| Submitted By: JB Bolger, Golf & Downtown Area Maintenance Manager |
|
| | | | | | | | Summary Statement:
| Final payment reflects a net decrease of $3,818.02. |
|
| | | | | | | | Expenditure Required:
| $115,181.98 |
|
| | | | | | | | Source of Funds:
| Capital Improvement Golf Course Improvement Bond Funds |
|
| | | | | | | | Background Information:
| This project addresses storm water runoff from the Sweetwater Circle/South Fork Lane neighborhood by installing 36" concrete storm sewer pipe under holes 14 and 15. |
|
|