| | | | | | | | CITY OF WATERLOO
Council Communication
Motion approving Change Order No. 4 with Cardinal Construction Inc., of Waterloo, Iowa, for a net increase of $13,960, in conjunction with the Five Sullivan Brothers Convention Center 2nd Floor Renovation Project, and authorizing the Mayor to execute said document.
City Council Meeting: 10/4/2021 Prepared: 9/14/2021 |
| | | | | | | | SUBJECT:
| Motion approving Change Order No. 4 with Cardinal Construction Inc., of Waterloo, Iowa, for a net increase of $13,960, in conjunction with the Five Sullivan Brothers Convention Center 2nd Floor Renovation Project, and authorizing the Mayor to execute said document. |
|
| | | | | | | | Submitted by:
| Submitted By: Noel Anderson, Community Planning and Development Director |
|
| | | | | | | | Recommended Action:
| Approval |
|
| | | | | | | | Summary Statement:
| COR 03 (PR01): Provide a new roof hatch to allow for greater access to the existing penthouse. |
|
|