Item Coversheet
CITY OF WATERLOO

Council Communication

Motion approving Change Order No. 4 with Cardinal Construction Inc., of Waterloo, Iowa, for a net increase of $13,960, in conjunction with the Five Sullivan Brothers Convention Center 2nd Floor Renovation Project, and authorizing the Mayor to execute said document.

City Council Meeting: 10/4/2021
Prepared: 9/14/2021
ATTACHMENTS:
DescriptionType
Change Order #4 - 5 Bros 2nd Floor RenoBackup Material
SUBJECT:
Motion approving Change Order No. 4 with Cardinal Construction Inc., of Waterloo, Iowa, for a net increase of $13,960, in conjunction with the Five Sullivan Brothers Convention Center 2nd Floor Renovation Project, and authorizing the Mayor to execute said document.
Submitted by:
Submitted By: Noel Anderson, Community Planning and Development Director
Recommended Action:
Approval
Summary Statement:
COR 03 (PR01): Provide a new roof hatch to allow for greater access to the existing penthouse.